Wednesday, June 1, 2011

MSD Carlow - 250 Litre Mobile Vessels For New Manufacturing Facility

Radleys were awarded the manufacture of two 250 litre mobile vessels for MSD’s new manufacturing facility in Carlow. These vessels are to be used in the production of biotechnology pharmaceuticals and were produced to the highest standards required for Bio- Pharmaceuticals. This project was in addition to our ongoing commitment to this facility.

Wednesday, December 1, 2010

Eli Lilly Kinsale

Radley Engineering were awarded the installation of Boiler 5 and the Natural Gas Ringmain at Lilly in Dunderrow. Now nearing completion, this included the removal of two boilers to be replaced by a single boiler of greater capacity. With the installation of the ringmain came the fitting of pressure control stations and all associated instrumentation.

Tuesday, June 1, 2010

Genzyme FFCE

Radley Engineering as the main mechanical contractor has completed on schedule the new Fill Finish Capacity Expansion project for Genzyme Ireland. This facility was completed over an 8 month period on site which involved the installation of 8,000 meters of pipe.
This project involved the installation of three lyophilysers and associated vial washing, filling and capping lines. Radley's also installed clean steam and PUW generators and all associated clean system pipe work. In addition to all of the clean systems above we also installed the air handling equipment and the HVAC systems.

Monday, March 1, 2010

Merck Sharp & Dohme Carlow

Radley Engineering main mechanical contractor have completed on schedule the new Merck Sharp & Dohme VBSF Facility in Carlow Ireland. This facility was completed over an 8 month period on site which involved the installation of over 17,000 meters of pipe and 133 modules.
This project also involved the installation of boilers, vessels, heating and cooling skids, vacuum pumps, compressors and other equipment. All associated pipe work including clean systems. These clean systems included vial and syringe filling lines as well as purified water and WFI loops. This project was as also award the CISE (construction Industry Safety Excellence) International project of the year title.
A European leader in the manufacture of high quality stainless steel and carbon steel fabrications.